Progress!  The footers are in, and the forms for the stem wall are in place.  Once they pour the stem wall, they will finish roughing in the septic connection under the foundation, then add a layer of radon rock inside the walls.  Then a vapor barrier goes on top of that, then foam, then the mesh with the electric heating elements, then the slab is poured!

Progress! The footers are in, and the forms for the stem wall are in place. Once they pour the stem wall, they will finish roughing in the septic connection under the foundation, then add a layer of radon rock inside the walls. Then a vapor barrier goes on top of that, then foam, then the mesh with the electric heating elements, then the slab is poured!